Hi folks ...
Until recently I have been able to add a resource from a Resource Pool to a task and set the Units to 0% initially - this had the effect of leaving work assigned to existing resources unchanged. BUT in the last week or two MSP has started to recalculate the Work assigned to each of the existing resources. I noticed that no matter what I put into the Units cell when adding the resource when I hit enter and MSP returns to the Task usage view that the Assignment Units shows as 100% and I am guessing that this is what is causing the problem.
Does anyone know why this might be? Have I inadvertently changed an option somewhere? Maybe MSP has changed and I didn't notice.
Running MSP 2010
Thanks
kevin
Until recently I have been able to add a resource from a Resource Pool to a task and set the Units to 0% initially - this had the effect of leaving work assigned to existing resources unchanged. BUT in the last week or two MSP has started to recalculate the Work assigned to each of the existing resources. I noticed that no matter what I put into the Units cell when adding the resource when I hit enter and MSP returns to the Task usage view that the Assignment Units shows as 100% and I am guessing that this is what is causing the problem.
Does anyone know why this might be? Have I inadvertently changed an option somewhere? Maybe MSP has changed and I didn't notice.
Running MSP 2010
Thanks