Using Project 2000 (9.0.2001.0219 SR-1)
I work in a Job shop environment.
I have been managing a master schedule using a resource pool file. What I have been doing is making projects & inserting them into the master schedule & then unlinking the projects. Then I assign resources to the tasks in the newly inserted projects. Then I have been manually leveling the resources. This has worked very well up until now.
I now have a need to work some of my resources overtime. I am not sure exactly how to do this. Now, I can change the working calendar for that resource for more hours on the day I need him to work the overtime. The resource is still shown as over allocated. The task calendar is my standard work calendar. I cannot change it on that day or it affects everything else using that calendar. Is there a way to add the overtime to that single task? I hope I am not way of base here.
I work in a Job shop environment.
I have been managing a master schedule using a resource pool file. What I have been doing is making projects & inserting them into the master schedule & then unlinking the projects. Then I assign resources to the tasks in the newly inserted projects. Then I have been manually leveling the resources. This has worked very well up until now.
I now have a need to work some of my resources overtime. I am not sure exactly how to do this. Now, I can change the working calendar for that resource for more hours on the day I need him to work the overtime. The resource is still shown as over allocated. The task calendar is my standard work calendar. I cannot change it on that day or it affects everything else using that calendar. Is there a way to add the overtime to that single task? I hope I am not way of base here.