If I have a scheduled task, such as a meeting that will last for 2 hours. There are four different resources that will participate in the meeting. How can I get ms project to show the resources independently time and the scheduled time at the same time ?
As I now assign resources to the meeting, 2 hours for each resource the work time becomes 8 h instead of 2 h.
I want to demonstrate that the activity is two hours long at same time as each resource is working two hours on the activity .
Is this possible?
/Gus, Sweden