phantom2120
MIS
MS Project 2002
Problem: Gantt Chart always shows a task graphically, even if the task doesn't yet have a valid Start/Finish date. Argh. I can't override the default Start/Finish date with "NA," which I hoped would suppress the Gantt graphic as well as show that the task doesn't yet have a valid date. This means that I have erroneous Gantt graphics and erroneous dates in my MS Project!
Situation: I have a set of 20 tasks/milestones that are considered standard to a process. Therefore, I do NOT want to delete any of these tasks, even if this project team chooses to ignore a given (standard) task or chooses to not assign a start and finish date yet.
Reasoning:
1. I'd like to communicate to the project team that a certain task, although usually standard, is NA (not applicable) for this project. I'd like it to be clear that a task was not "left out," instead, it was "intentionally left blank." Maybe I want to use the Note column to explain why the date is "NA."
2. I'd like the Gantt chart to be blank for that task, because it is only a placeholder for a normal process.
3. I certainly DON'T want the Start/Finish columns to show a bogus, default date! (MS Project defaults to the Project Start Date.
WORKAROUNDS? Solution?
Thanks in advance!
Problem: Gantt Chart always shows a task graphically, even if the task doesn't yet have a valid Start/Finish date. Argh. I can't override the default Start/Finish date with "NA," which I hoped would suppress the Gantt graphic as well as show that the task doesn't yet have a valid date. This means that I have erroneous Gantt graphics and erroneous dates in my MS Project!
Situation: I have a set of 20 tasks/milestones that are considered standard to a process. Therefore, I do NOT want to delete any of these tasks, even if this project team chooses to ignore a given (standard) task or chooses to not assign a start and finish date yet.
Reasoning:
1. I'd like to communicate to the project team that a certain task, although usually standard, is NA (not applicable) for this project. I'd like it to be clear that a task was not "left out," instead, it was "intentionally left blank." Maybe I want to use the Note column to explain why the date is "NA."
2. I'd like the Gantt chart to be blank for that task, because it is only a placeholder for a normal process.
3. I certainly DON'T want the Start/Finish columns to show a bogus, default date! (MS Project defaults to the Project Start Date.
WORKAROUNDS? Solution?
Thanks in advance!