    Using MS Project 2000 I have created a filter that displays what I want to see in Project. I have figured out how to save as a web page using this filter. My only problem now is that I cannot figure out how to keep the data sorted by the start date in this saved web page. I think I need to...
  2. Fish2000

    A little template help

    I tried what you said but the problem remained. Then I had a brainstorm. I renamed the problem template file (abc.mpt). I opened abc.mpt. I then started a new file. I set up the new template identical to abc.mpt, then copy & pasted the tasks from abc.mpt into the new file. I saved this new...
  3. Fish2000

    A little template help

    Using MSproject 2000 When doing a "Save As" of a template "Filemname.mpp". Under File | Properties | Summary, the title takes on this new file name as the title. This is what I desire. But now I have created a template that will not behave in this way. Help! I don't understand how this...
  4. Fish2000

    Need help with a formula

    Found the button, and it worked. Thank you very much!
  5. Fish2000

    Need help with a formula

    Using Project 2000 I made a custom column to give indicators to show if a task is real late, running ahead, or almost on time. I have set up the custom column as follows: I have a formula: (now()-DateValue(Finish)). I have graphic indicators set up as follows: greater than 2 (red frown) less...
  6. Fish2000

    Assigning overtime to resources

    Using Project 2000 (9.0.2001.0219 SR-1) I work in a Job shop environment. I have been managing a master schedule using a resource pool file. What I have been doing is making projects & inserting them into the master schedule & then unlinking the projects. Then I assign resources to the tasks...
  7. Fish2000

    Too many calendars!

    Thanks for the help! I am still going to have to go through each individual project and delete the extra calendars though.
  8. Fish2000

    Too many calendars!

    I'm using Project 2000 SR-1. I have a master project with about 40 inserted projects all using the same shared resource pool. I recently had my resouce pool file get corrupted. Using my master project file I was able to sort of recreate a new resouce pool by copying resources into a new...