The default for me is to auto calculate but it doens't same to be adding up the resources hours. Is there anything else I need to check in my MS Project set-up?
Is it possible to have MS Project 2000 sum up all resource hours allocated to the sub-tasks on the summary task? Right now I have to manually calculate the total hours for a summary task and it's very time consuming.
Thanks in advance
Thanks alot. Everything is working well now. I'm still having trouble with the saving all of this to .pdf. I would like to create a separate file for each project desc. Can this be done?
I am currently using Access 97. I have a 50 page report that I would like to save as separate reports for each one page record on the report. I would like to key off the project desc field. Can anyone help me with the coding of this in a macro or module? Thanks in advance