I think it IS arbitrary the way the work hours of the task are estimated. I believe the faculty member builds the task list, then looks at a resource and (going down the task list) assigns 2% on a task and 30% on another task and 9% on another task until it all adds up to 100%. Then they see...
This is my first interaction with how universities run grant projects - and its different (the term weird also works) :)
The 9% is Resource Z's work on a specific task. In other words, it is 9% out of 100% of his commitment. If you add up all of Resource Z's assignments on this project, it...
I'm creating a plan for a university, which looks at resource time not in hours but as a percentage of time available to the project when doing their planning. I can't figure out how to do this. Here are the details:
>The total number of hours available for the year is 1950 (which I addressed...
Thanks for looking into this. I deleted the task and it did fix the overallocation. However, when I added it back I'm overallocated again. The steps I followed were:
1. Gantt Chart view delete the task (then went to Resource Usage to make sure overallocation was gone)
2. Gantt Chart view...
I'm building a project plan to demo some MS Project capabilities. For some reason Project is indicating that some resources are overallocated. I cannot determine why. If it were a task setting, other resources on those tasks would also be overallocated (which they are not). I would attach the...