Its good to have somewhere to sound ideas and ask questions there are only 2 or 3 of us in my company despite its size that use MSP to any extent.
Cheers Alex
Thanks Julie,
The buffer tasks do need to be between the two end dates and this is the simplest way of ensuring any change in CP will ensure the buffers stay on the CP therefore I don't mind the Buffer tasks being measured on the critical path I just don't want to have to update the...
Hello everyone,
I would like to know how to total up all the durations on the critical path so I can see how long the critical path was before and after updating and rescheduling. Is there a simple solution other than exporting durations and totalising them after filtering for CP...
Sorry Julie / everyone, I didn't realise you have to sign up to the 4shared to view the file, does anyone know of a free and open file sharing solution where I don't have to give my credit card details? Cheers Alex
Hi Julie,
Thanks for your reply. Yes that is the case however the Total Slack indicator wouldn't depict what our client wishes to see. In addition to that if there is slack in the system the critical path will as far as I am aware only show the Contractual completion date as it will be...
Hi Everyone, Lets see if I can explain this properly, I am a planning engineer and I am currently looking after a Scheme where we have reduced the programme (removing hidden float) and we have agreed with the client that we will track our Reduced Target date against his Contractual completion...
Thank you guys very much, As it happens PDQBatch your info was very salient as my boss has recently upgraded me to 2010 so that's a real help and Julie thanks for the tip that would definitely have been a good way around it although potentially onerous. Its also really nice to have people agree...
Hi Guys I am new and hoping you can help. I have a scenario where we have been asked by the client to price for extra works so we are also obliged to enter them into the programme. Unfortunately they go beyond the end of the current critical path and the end date of the project. As they are...