Hi Steve,
I've ensured the tasks are not effort driven, the resources are entered correctly & the dependency links are standard (i.e. not ff or ss or fs+x) so I'm still at a loss!
DG
I'd the easiest way (thinking that you may want to resort it another way in the future) is to highlight a line, then drag & drop it where you want.
WARNING - check the dependency links you had didn't change!
Hi All,
When I update a task (duration extends for example) I am expecting it to change the date of its successor, which is a normal FS link, no restraints & no other predecessors. However it doesn't change unless I save, close & reopen! I remember there being a 'refresh/recalculate' button on...
The date filter I use all the time (mainly to see where I need to update my plan, check my staff have updated their plans & to provide resources with their deliverables/ tasks in the coming days/ weeks/ months) is the 'should start/finish by' filter, which can be found within the drop down bown...
Hi all,
I've got a project plan, that ISN'T effort driven, that although the individual tasks are full days (1, 2, 3 etc and not 1.5 days for instance) the header is showing that all of them are 55.34 days to complete?!
This is driving me mad as I know this happens for effort driven projects...