Thank You PDQBach, The mistake I was doing all this while was manually entering the start/finish dates instead of entering "3y" in duration.
That change worked for me.
Thank you once again.
Thank you PDQBach, but for this to succeed I must have a resource that is only working for 5 hrs a month correct? What if its a vendor related task, and the vendor has other normal operating hour tasks in the WBS?
Would the only option for me would be to create a custom calendar with the 1st...
Hello all, This is my first post and its a question with which I need help with. More information below:
I need to setup a task in the WBS (where task durations are in days or hours.) I have a task which is over a period of years and only a certain amount of hours needs to be dedicated every...