  1. LauraLeff

    Incorrect Resource Allocation

    Try this... * Go to Resource Usage View * If needed, change the timescale to the bottom units being days * Do a timephased edit between the two resources, setting the second shift's hours on the task to 0 and the first shift's hours on the task to 4. I think that will get you there.