Hmm, that's what I thought as well but here's what I'm seeing.
Create a new task that is Fixed Duration, effort driven.
Set a start date of 1/30/09 with a duration of 16 days.
Assign 1 resource.
Set the work to 2 hours, which automatically appears as 2% units for the resource.
No deadline...
So it seems I need to be using a fixed duration task and manually entering the hours I think the task should take the resource and the units will be calcualted automatically.
This seems to work when setting up the task but if I go back to a task and change the hours of work the Units never...
Hi,
I have a task that I want to have a fixed duration of say two weeks, May 1st to May 15th. I also have 3 resources that will work on this task for roughly 2 hours each (don't care when) over the two week task duration. So I would like to show the task as two weeks long and the two hour work...