MS Project fails to update date fields.
This is with an existing projects with there are no fixed dates.
I've noticed this in 2 circumstances:
First when entering %cent complete. This does not change any dates.
Second when changing the date of a task that was due prior to "now" but which is...
MS Project fails to update date fields.
This is with an existing projects with there are no fixed dates.
I've noticed this in 2 circumstances:
First when entering %cent complete. This does not change any dates.
Second when changing the date of a task that was due prior to "now" but which is...