Thanks for the initial response. Yes, I have been looking into the issue on similar lines, but do not have a clue yet... Manually changing the plan is possible but considering 1000+ lines in the plan, am looking for one time change. Will keep looking out...
Am working on Projects 2000 and have merged some projects into one Master project plan.
However the durations types are different (some tasks show in Mins, some in weeks and some in hours).
I would like to change the view to reflect one Unit of Measure across the plan (be it either Mins, hrs or...