HOWEVER, "Hide task bar" does NOT keep the date information from impacting the rollup task graphic.
For example, If there is a parent task called, "RESEARCH" and there are two subtasks, "TYPE A" and "TYPE B"
and this project isn't going to use TYPE B, so we "Hide task bar"
the...
User can supress the task from the Gantt Chart by double-clicking on the task and checking "Hide task bar"
But now how to get rid of that date from the Start/Finish columns?
MS Project 2002
Problem: Gantt Chart always shows a task graphically, even if the task doesn't yet have a valid Start/Finish date. Argh. I can't override the default Start/Finish date with "NA," which I hoped would suppress the Gantt graphic as well as show that the task doesn't yet have a...
I found a limitation of the Linksys broadband router: two computers can't open simultaneous VPNs. They step on each other.
So I figured that I'd try using RRAS, DHCP Client and DHCP Server all on the same 2000 Adv Server Box. So far, I'm stumbling (things are a little different than NT4 and I...
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.