Hi Julie,
I found the solution, although it seems strange to me.
I checked the start dates of the subprojectgs again. They were the same as they should be (the one of the main projectg). But I typed this same date anew, and everything changed to the situation that should be: so good connection...
Hi Julie,
Just after my response to you I was glad with the solution, but there is still something wrong. I will explain the project/problem:
Project exists of: A-M-B-N-C-O-D-P-Q. All tasks are normally linked as start-after-end. MNOPQ are tasks in the main project. ABCD are inserted...
MSProject 2003. A rather simple project, with several subprojects and a few normal tasks in the main project. One of the sub-projects has a start to end relation to one of the tasks in the main project. But the result is (consequently) that it starts at a specific date (3 months later). I did...
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.