The approval is a milestone. Your suggestions makes the 5 tasks dependent on the approval. I want the approval dependent on the 5 tasks, but to occur 10 days before the start of the earliest of the 5 tasks.
Thanks for trying.
Todd
This is a little complicated. Let’s say I have 5 or so separate installation activities that each require the same WAP approval. Each of the these 5 activities have completion dates that move around a lot. I’d like the WAP done 10 days before the earliest of these 5 activities. How do I tie...