Hi Julie,
Thanks for your response. I had decided to put it in hours, but was asked to ensure there was no way around that! Our '20' hour shift is contracted work. The schedule I am creating is not intended to break that into resourcing shifts, we just need a start and end time for their...
Yes - I do have multiple calendars - that's what I'm working inside. My calendars don't seem to overwrite the duration of the project calendar. I.e. if my 'new' calendar is 12 hour days, 1 'day' still shows up as whatever is set in my project calendar. (Default is 8 hrs)
Hi,
I'm new to MS Project (using MS Project 2010) and am working on a schedule where some of my tasks are on a 20 hr/day schedule (construction) and others are on a 8 hr/day schedule. I've tried making task and/or resource calendar changes, but from what I can tell I'm restricted in my...