Thanks
it appears to us that the subproject managers have added their own resources instead of using the resource pool. Additionally they have copied the project file to fill their part in and then added it to the Master file.
New to all of us. Thanks big for your help
Hi JulieInMain,
thanks again for your help. We checked the first tip of your previous message and found out, that although we only imported (referenced) three files, it shows much more in the resourcen usage view, which is strange.
I think we all use the same resource pool and share it...
Hi JulieInMaine,
the last I can answer: Yes, we have imported them as References to the master project file.
I suppose the latest service pack is installed. MSP says it is version: 14.0.7106.5003
The project field I have not done, so I will check.
Thanks.
Bumpui
Dear all
I ran into a weird situation with MS-Project 2010,
I entered a task in the Gantt View. I added resources, the usage of their utilization etc.
The task is based on units.
When I use the resoure usage view, I suddenly see the task below the ressource mentioned four times and the hours are...