Thanks for the reply. The situation I've described is just an example. My real problem is that I have a machine that is used by a human resource for some amount of time. Before it is able to be used again it needs to be cleaned be the cleaning team. So I have task1 -> task2 -> task3. Since I...
Hi!!!
Imagine that I have a 2h task with two resources assigned and I want resource 1 to work 0,5h at the beginning, resource 2 1h after the inicial resource 1 work and finally another 0,5h of resource 1 at the end. I could do this with three connected tasks each with its own resource. However...
Thanks for your help.
In fact machine only do work when operated by a worker. However I have different groups of workers, each with its own calendar, that can operate the same machine. To cope with this, I use a 24H calendar for the machines in order to always have a common calendar period that...
Hi!!!
I'm starting to build some projects using MS Project and I'm facing some issues.
The projects I'm building have several subprojects embedded and they all share resources (machines and workers). Although machines are workers dependent, I need to use both resources in order to avoid both...