Dear all,
I've suddenly studied more about formula of custom field.
I guess I got a work around by creating a 2 fields :
Duration1 : ProjDurConv(ProjDateDiff([Current Date]+1.[Baseline Finish]), pjDays) <--- this is for calculation for the Ms Project engine
Text09 : IIf([% Complete]<>100...
Thanks, Skip.
I am sorry I don't understand your suggested solution. I am sure it is my question not clear enough. Can you try help me again in my latest post "Delay Days Indication" ?
Thanks for your kindly help.
Hi,
I want to run a status report everyday, to the status of each task, I can't find any field to show how many days the task is delayed even it is not finished. The situation is as the following :
baseline start day baseline finish day
Task AA - Day01...
Hi,
I want to have a column that can show how many days is really delayed while the task is even not finished yet. I try to use a duration1 and use the formula to calculate : Current Date - Baseline Finish Date, but it didn't work. Please help.
On the other hand, I would this figure show 0 if...
If quantity is really important. I would rather separate one task into ten :
Task A 01
Task A 02
.
.
Task A 10
This is just my preference, let see PDQBach have any suggestion ? :)
Hi,
Let me share my point of view.
In such case, I seldom manage the quantity in this way. Only the task activity is the most important to manage. Especially in this case, just number of tasks x quantity, I will just at the quantity on the task name " x 10" to handle it. Then I can check the...
Hi,
I am using MS Project2003 Professional.
I inserted a some custom date field (date1, date2)
I found that if I didn't entry data to the cell, it will appear "NA", can I change it to appear nothing? or just a symbol "-" for easier reading?
On the other hand, is there any "condition...
Thanks.
Sorry for my blur question.
I want to enter and estimate the duration by normal working days. But I want to know how long it is including non-working days.
for example :
in 5 Day work calendar (Mon-Fri)
entered duration : 3 days
If the start day is on Mon, so it will be Mon to Wed...
Sometimes 2 task have dependency for Starting, and different dependency for finishing.
How can I solve this problem ?
Example :
Task A
Task B
Case 01:
A start, then B can follow to Start. (Start-to-Start)
A finish, then B can follow to Finish. (Finish-to-Finish)
Case 02:
A Start, then B...
Hi,
I really confuse how can I adjust the column width of the reports ?
for example :
http://www.geocities.com/bestchild10cc/mspjq02_a.jpg
I want to decrease the width of every column, but seems it cannot be set.
i am sorry for my idiot question.
Thanks for you kindly help.
Benson
4) Then, I choose back "Days" again, and press "OK"
http://www.geocities.com/bestchild10cc/mspjq01_d.jpg
http://www.geocities.com/bestchild10cc/mspjq01_e.jpg
5) Run the report again, The problem is fixed !!!
http://www.geocities.com/bestchild10cc/mspjq01_f.jpg
Why ??? Ha Ha !
Or anything I...
2) Then,
Click on: View | Reports
DoubleClick: Assignments
SingleClick: Who Does What When
SingleClick: Edit Button
SingleClick: Definition tab
http://www.geocities.com/bestchild10cc/mspjq01_b.jpg
3) Then, I try to pull down the menu, choose "Weeks"
***BUT NOT CLICK "OK" YET ...
Thanks very much, by the way, I found something strange, it seems I did nothing but the problem is fixed :
1) I open the mpp file then run the report,
the "##### problem occur."
http://www.geocities.com/bestchild10cc/mspjq01_a.jpg
Hi,
When I want to print a report eg. "Who Does What When", some of the work hours are too long, the report appear as xxxxx, I want to adjust the column width but I can't find, can anyone kindly so me?
Thanks.
Benson Poon