I'm using an excel worksheet with automatic graph based on advanced filter.
I protect my project with password but when I want to save the workbook, there is message informing me that I can not save this file when project is protected!!?
Excel crash....and when I wanrt to reopen the...
When workseet is not protected, users can cancel formulas when typing in cell with formulas.
I would like to know if there is a way to rest all formulas in a sheet.
Excact ,with the following conditions:
If $D$1 =1: working days are monday to saterday excluding holidays
If $D$1<>1: working days are monday to friday excl.holidays
Yes for both.
I try the following:
=IF(D1<>1,WORKDAY(A1,C1),A2+NETWORKDAYS(A1,A2)-DATEDIF(A1,A2,"d")+SUM(IF(WEEKDAY(A1-1+ROW(INDIRECT("1:"&TRUNC(A2-A1)+1)))=C2,1,0)))
I would like to calculate :
End Date (B1)
from a Start Date (A1)
+ Duration (C1) in Working days (without WE & holidays)
BUT
if cell D1=1 ,Saterdays are working days too.
WORKDAY function consider only monday to Friday as working days!
How to do it?
I would like to calculate :
End Date (B1)
from a Start Date (A1)
+ Duration (C1) in Working days (without WE & holidays)
BUT
if cell $D$1=1 ,Saterdays are working days too.
WORKDAY function consider only monday to Friday as working days!
How to do it?
In the 1st Sheet Column A, I introduce list of articles (text).
I would like to know if there is a way to create automaticaly in Sheet 2 Column A a list of all articles sorted alphabeticaly ; Same articles may appear several time in Sheet1 but ONLY once in Sheet2.
There was error in my question ("0" instead of ")"
Correction:
I would like to calculate a End Date (B1) from a Start Date (A1) + Duration (C1) ; Duration in Working days (without WE & holidays) BUT including saterdays (this is the problem!)
function WORKDAY can calculate a date from start Date & duration , excluding weekends & holidays.
How to calculate a date , excluding holidays but including weekends?
I would like to calculate a End Date (B1) from a Start Date (A1) + Duration (C1) ; Duration is in Working days (without WE & holidays) BUT including saterdays (this is the problem!)
I would like to calculate a End Date (B10 from a Start Date (A1) + Duration (C1) ; Duration in Working days (without WE & holidays) BUT including saterdays (this ids the problem!)