I was charged with developing MS Project plans for about 40 projects, most of which have been in progress for a while (some are halfway through, some almost finished, some have a year left, etc). These plans will be used to track progress rather than to schedule activities. (I realize this...
I want to do something very simple (I think) and basic to Project but it's not letting me.
I want to create a central resource pool which would be shared across projects. This pool would list employees and their specialities (technology, research, evaluation, etc). Projects would be attached...
Thanks, but... The recurring task ("monthly report") showed up on the Gantt chart fine (one day for each report). In the task list, though, the "duration" became the cumulative number of days from first to last report. so it looks like 43 days are required to write 3 monthly reports (which...
I'm a relative newbie to the MS Project world. Can someone tell me how to set up tasks that are to occur at fixed intervals (such as monthly reports, updates, etc)? I'm using Project 2003.
Thanks,
Larry