Thanks for that Julie. It is just this file that seems to be the problem - I think the answer is going to be restoring it to before I started having problems. I had made quite to few changes with filters, flags and some other bits and pieces so think losing a few days' worth of updates to the...
I'm hoping you can help. I have a programme set up that I want to switch from the Gantt Chart view to Resource Usage view. This has never been a problem before, but for some reason it now just flicks briefly onto Resource Usage and then back to the Gantt Chart. The same thing happens when I...
I'm setting up a programme for a construction site, looking forward to the next year or so. Some of the houses are definitely going ahead, while others are only projections based on sales budgets. I set up a flag field in the Gantt chart and formatted it so that it was clear at a glance which...
Hi,
Is there an easy way to copy flag information I've set in a Gantt chart across to a resource view? I know I could go through and reset the flag in both views, but just wondered if there's a quicker way to do it?
I'm using Project Standard 2013.
Thanks.
Thanks folks, I'll try both of those and see how I get on. The report is going to be distributed to a lot of people, most of whom don't use Project, so I'm trying to get it as clear and "idiot proof" as possible :)
Thanks again for the help.
Hi,
I work for a construction company, and am setting up a programme for our factory that makes the timber kits for the houses so that we can get an idea of what capacity will be needed over the coming year. The programme is split into 2 parts - the first is for kits that are definitely...
Yes, it's for our contracts manager organising subcontractors, so I would need to see the resource information. It's not the end of the world if it can't be done - I just though I would double check in case there was something obvious I'd missed.
Thanks for your help.
Is there a way of formatting the table on the right hand side of the task usage view so that for each task, any days with work assigned show as a shaded cell rather than the amount of work (e.g. 8h or 1d)? I've tried going through all the formatting options I can find and none of them seem to...
Hi,
I'm using Project Standard 2013 (version 15.0.4551.1507), and have just encountered a weird problem that I've never seen before and wondered if anyone can help.
I have a number of projects, which were all set up from the same template and which are updated with weekly progress. Some of...
Just thought I'd post a quick update... After weeks of waiting for my IT department to look into this, I opened the document back up this morning - to find that the problem isn't happening any more. Not sure why not, unless there's been an automatic update since January that's fixed it, but at...
Thanks, I've tried the link but am still getting the same error message. I've spoken to my IT department about it and am waiting for them to get back to me.
This is the first time I've tried to install any updates. I checked with someone from our IT department before I downloaded it and they didn't mention that it wouldn't install - I might check with someone else though, just to be sure! And, of course, the manager for this project is desperate...
I've had a look at the installed updates, and don't see either the April or December one. Presumably if they were installed the dates shouldn't still be moving though?
Damn, I thought for a minute my problems were solved! I'd checked on the Microsoft support site, and their automatic detection software said I was running a 64 bit operating system, so I downloaded the 64 bit hotfix. But I've just double checked, and it's the 32 bit version of Project I have...
Hi,
I'm using Project Standard 2013. I had one of my projects set to the resource usage view, but discovered that some of the task dates changed when I tried to print it, and did not follow the non-working time set in the project calendar (working days Mon - Fri, with a holiday set for Mon...
Hi Mike
The steps were pretty much as you said:
1) I created the 6 individual subprojects, including setting flags 1-7, and saved them
2) Opened a new file and saved as the master project for the first department
3) Inserted each of the subprojects (Project ribbon - clicked Subproject -...
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.