    Change color of several tasks at once

    Hello everyone, I am looking for way to change the colours of some of my task bars all at once (one by one takes quite a long time) Is there a way to select all the bars I want at once and modify their colours? Thanks for your help. JEan
  2. Jeannot1984

    MS project: resource graph <> plot resource chart: FTE against months

    Hi everyone, I am sorry it took so much time before my reaction. So first thanks for your help, it is working good now. I now have another question on top: I have a certain number of people working on different projects (on week 1: A -5%: B -6%, C-20%, on week 2: A -7% B-3% and C-40%) and I...
  3. Jeannot1984

    MS project: resource graph <> plot resource chart: FTE against months

    Hi All, I would like to plot custom resource chart in MS project. Basically, I need to plot the amount of full time employment (FTE) against the number of month. It means I plot a 100% bar when I have 1 person working 100% of its time, 200% for two... So far I could just plot the number of...