Hello everyone,
I am looking for way to change the colours of some of my task bars all at once (one by one takes quite a long time)
Is there a way to select all the bars I want at once and modify their colours?
Thanks for your help.
JEan
Hi everyone,
I am sorry it took so much time before my reaction.
So first thanks for your help, it is working good now.
I now have another question on top:
I have a certain number of people working on different projects (on week 1: A -5%: B -6%, C-20%, on week 2: A -7% B-3% and C-40%) and I...
Hi All,
I would like to plot custom resource chart in MS project.
Basically, I need to plot the amount of full time employment (FTE) against the number of month. It means I plot a 100% bar when I have 1 person working 100% of its time, 200% for two...
So far I could just plot the number of...