Workgroup teamstatus message updating durations??

Status
Not open for further replies.

PatSalmon

Technical User
Jul 5, 2001
27
CA
I am testing the workgroup functionality in Project 2000. When ever I respond to a teamstatus message (for example: a task with a duration of 1hr, I enter 0 in the "Remaining Work" column and 1hr in the column for the entire period. When I click the update button the duration for the task gets updated to 40 hours. I would really like to use this feature but I don't feel comfortable with these results. Does anyone have any tips?

Thanks
Pat
 