Work Column - query

Status
Not open for further replies.

kaney

IS-IT--Management
Jan 27, 2005
32
0
0
GB
When the work column is populated it can be displayed in hours or days.

To change the settings as a whole obviously i go to Tools \ Schedule \ Work is entered........and choosing the option of days or hours etc

A PM has asked me if Days are set in the overall settings as above is there a quick way of changing the column to hours without amending the settings above???? Basically he just wants to check the work column without amending any major settings

Ive checked but cant see any other way other than by changing settings,

PLease provide any ideas

Kane
 
Tools | Options | Schedule-tab is the only way to change the display.

The option is project-file specific so you can have two files open simultaneously with 1 having "days" and the other having "hours".
 