meetarchna
IS-IT--Management
Hi
I am inserting a column which is of type work into my .mpp
Microsoft Project calculates total work as the sum of the work that all assigned resources are to perform on a task. This is based on the assignment span, the number of resources assigned, and the assignment units for the assigned resources. Work includes actual work and remaining work, as well as overtime work.
My problem is that by default MSP takes 8 hors as working hors per day. though I have changed the working hours to 9 in calender thru tools->options->calender , still the calculation of work column is happening as per 8 hrs a day
Any Clue to solve this problem
Thanks in Advance
I am inserting a column which is of type work into my .mpp
Microsoft Project calculates total work as the sum of the work that all assigned resources are to perform on a task. This is based on the assignment span, the number of resources assigned, and the assignment units for the assigned resources. Work includes actual work and remaining work, as well as overtime work.
My problem is that by default MSP takes 8 hors as working hors per day. though I have changed the working hours to 9 in calender thru tools->options->calender , still the calculation of work column is happening as per 8 hrs a day
Any Clue to solve this problem
Thanks in Advance