Like many people I tend to play with MS Project without really understanding it. Can someone please help me understand how Work is calculated. I have been provided a plan where the the outline parent task contains 2 x resources of 50% and the sub tasks work adds up to 6 days of work. When I enter these tasks into another plan (and also calculate as Duration x Units) I get a total of 64 (58+6) days, the plan provided gives me 62. Can anyone explain what may be happening?
Provided Plan
Task Work Duration Resources Type
Outline 3 [blue]62[/blue] days 58 days 2 * 50% Fixed Duration
Outline 4a 1.5 days 16 days 1 * 9% Fixed Work
Outline 4b 1.5 days 16 days 1 * 9% Fixed Work
Outline 4c 1.5 days 16 days 1 * 9% Fixed Work
Outline 4d 1.5 days 16 days 1 * 9% Fixed Work
My Version:
Task Work Duration Resources Type
Outline 3 [red]64[/red] days 58 days 2 * 50% Fixed Duration
Outline 4a 1.5 days 16 days 1 * 9% Fixed Work
Outline 4b 1.5 days 16 days 1 * 9% Fixed Work
Outline 4c 1.5 days 16 days 1 * 9% Fixed Work
Outline 4d 1.5 days 16 days 1 * 9% Fixed Work
Many Thanks
Simon Rouse
Provided Plan
Task Work Duration Resources Type
Outline 3 [blue]62[/blue] days 58 days 2 * 50% Fixed Duration
Outline 4a 1.5 days 16 days 1 * 9% Fixed Work
Outline 4b 1.5 days 16 days 1 * 9% Fixed Work
Outline 4c 1.5 days 16 days 1 * 9% Fixed Work
Outline 4d 1.5 days 16 days 1 * 9% Fixed Work
My Version:
Task Work Duration Resources Type
Outline 3 [red]64[/red] days 58 days 2 * 50% Fixed Duration
Outline 4a 1.5 days 16 days 1 * 9% Fixed Work
Outline 4b 1.5 days 16 days 1 * 9% Fixed Work
Outline 4c 1.5 days 16 days 1 * 9% Fixed Work
Outline 4d 1.5 days 16 days 1 * 9% Fixed Work
Many Thanks
Simon Rouse