davidd31415
Programmer
I am using a 24/7 project calendar, 24hr work days, fixed duration / effort-driven tasks.
MSP2003 is splitting the end of a task on me and I do not understand why.
Here is an example:
With the above settings, I create two 5 days tasks.
I add one resource with a standard calendar.
I assign the resource to both tasks.
The first task looks fine. The second task levels to the proper position, starting right after the first task but only shows work for the first 2 days; after that it looks like a split but it stays like that into the weekend.
I've seen this behavior where another task with the resource starts on the same day the splitting task starts to split.
Any ideas?
Thanks,
Dave
MSP2003 is splitting the end of a task on me and I do not understand why.
Here is an example:
With the above settings, I create two 5 days tasks.
I add one resource with a standard calendar.
I assign the resource to both tasks.
The first task looks fine. The second task levels to the proper position, starting right after the first task but only shows work for the first 2 days; after that it looks like a split but it stays like that into the weekend.
I've seen this behavior where another task with the resource starts on the same day the splitting task starts to split.
Any ideas?
Thanks,
Dave