Hello,
I am a newbie to the Crystal thing, and am trying to come up with a function that will calculate the number of weekdays (Exclude Sat + Sun) between two dates.
Any ideas?

Thanks
Mike

 
There is an example of this between the CR help files. You will need CR8.0 or above to use the DateDiff function

//Crystal syntax
Local DateTimeVar d1 := {Orders.Order Date};
Local DateTimeVar d2 := {Orders.Ship Date};
DateDiff ("d", d1, d2) -
DateDiff ("ww", d1, d2, crSaturday) -
DateDiff ("ww", d1, d2, crSunday)


 
Check out 1b of the FAQ's 'Common formula examples' by Ken Hamady. Although I haven't used that specific formula, I have tried quite a few of his and found them easy to follow and they work!
 