Jun 28, 2006 #1 Acydman IS-IT--Management Nov 18, 2004 52 GB Does anyone know how to calaculate the working or week days between two dates? The formula i have at the moment is: {@SLA Date}-CurrentDate and i need to know who many working days are between those dates. Many thanks Mark
Does anyone know how to calaculate the working or week days between two dates? The formula i have at the moment is: {@SLA Date}-CurrentDate and i need to know who many working days are between those dates. Many thanks Mark
Jun 28, 2006 #2 teknogeek9 Programmer Jan 6, 2001 47 US I think you will find what you are looking for on Ken Hamady's website. Here is the link... http://kenhamady.com/form01.html Upvote 0 Downvote
I think you will find what you are looking for on Ken Hamady's website. Here is the link... http://kenhamady.com/form01.html