how do ,happy new year

I have 2 customers with callpilot 150's
one 1.5 the other 3.0
want to upgrade to 3.1 on both
question is: do i need to use the upgrade card
or can i just backup old database and restore in to new software, and re input key codes if needed

thanks

HALLOWED ARE THE ORI

mike
 
It would be best to get the upgrade on a card then upgrade, this would be no cost since upgrade is free from Nortel site for vendors. Purchase a RM CP and sell with your 3.1 software.

However both the same, no need to re-install codes but backup is a good idea if need to go back.

=----(((((((((()----=
curlycord
 
I have been doing these upgrades for years & all I do is take take the PCMI card out of the Call Pilot & put it in my laptop. I take the files that are on the card & delete them from the card. I usually save them to a folder on my laptop just in case. I then copy out the files of the latest 3.1 software to the now blank PCMI card,eject the card & place it back in the Call Pilot. Power up the Call Pilot & you are good to go. I have done over 100 systems & had maybe one or two fail to work.In the event of a failure just copy back your old software files & the system will work fine.
 
no need to buy the $500 card from Nortel, you can pick up a MPCI card at your local computer store.
 
just to finish this thread
i backed up the systems
swapped cards to new software level
restored programming
(note: new software card ,system lost keycodes,restore put back in)
all works

thanks