How could I update a project using the '% complete' making the program update automaticaly the actual start date ?
when i do the update the program fixes the actual start = baseline start and push the progress activity bar to a date after the updade. What i need is that the program calculate the actual start based in the % complete, and if necessary push the real start to a date before the assigned in the baseline start, in a way that the status date it coincides with the end of the work complete.