First of all I'm not even close to being an expert using MS Project so I hope my questions are easy for.
A co-worker of mine developed a 300 line item schedule using MS Project (2000). He asked me to take a look at it because his total project time span was 8 months but the roll-up of the project duration was 668d?. I looked at the outling (summary tasks/children) and everything looks fine. What's going on here most likely? What do the question marks mean after each duration?
A co-worker of mine developed a 300 line item schedule using MS Project (2000). He asked me to take a look at it because his total project time span was 8 months but the roll-up of the project duration was 668d?. I looked at the outling (summary tasks/children) and everything looks fine. What's going on here most likely? What do the question marks mean after each duration?