I'm using Project 2000 SR-1.
I have a master project with about 40 inserted projects all using the same shared resource pool.
I recently had my resouce pool file get corrupted. Using my master project file I was able to sort of recreate a new resouce pool by copying resources into a new resource pool file. But all the resources got scrambled in all the sub-projects. I am guessing that the internal IDs for the resources in the new pool are different somehow. So now I have to go thru every task & reassign the correct resources.
Here is the question, all of my projects seem to have created new calendars (standard1;standard2; etc.). Is there a way to delete all of these unwanted calendars or any unwanted calendar for that matter. I have made sure that these calendars are not being used. It is a real pain to scroll thru all these unwanted calendars for every task.
ps. Before you say it, I am now making our nework guy back me up each night.
I have a master project with about 40 inserted projects all using the same shared resource pool.
I recently had my resouce pool file get corrupted. Using my master project file I was able to sort of recreate a new resouce pool by copying resources into a new resource pool file. But all the resources got scrambled in all the sub-projects. I am guessing that the internal IDs for the resources in the new pool are different somehow. So now I have to go thru every task & reassign the correct resources.
Here is the question, all of my projects seem to have created new calendars (standard1;standard2; etc.). Is there a way to delete all of these unwanted calendars or any unwanted calendar for that matter. I have made sure that these calendars are not being used. It is a real pain to scroll thru all these unwanted calendars for every task.
ps. Before you say it, I am now making our nework guy back me up each night.