Hi,

Can anyone tell me how the time scale (for Start/Finish columns) can be changed in the Gant Chart view from Days (mm/dd/yy or other format) to time (HH:MM). I have a project file that appears in HH:MM format on a colleagues PC, but when I open it, it shows up as mm/dd/yy format. I'm sure this is a 'setting' issue, but where?

Any help will be greatly appreciated. Thanks in advance.:
Regards
MontyR
 
Tools...Options....Date Format.

Bear in mind that if the duration is greater than 24 hours your Start/Finish columns will look a bit weird.
 
Tools...Options....Date Format.(on the VIEW tab)

Bear in mind that if the duration is greater than 24 hours your Start/Finish columns will look a bit weird.
 