Templates that use 'Deadline' 2

Status
Not open for further replies.

planetant

IS-IT--Management
Mar 15, 2005
55
US
Is it possible to create templates that use the column 'deadline' so that the deadline is changed when the start date changes?

 
Surely a deadline is something that doesn't change when the start date changes? Otherwise its not a deadline.

 
You can right-click in Project over a column heading and rename it to anything you like. For instance, "End Date" could be "Deadline" or "Pretty Much when we'd like to be done"

D.E.R. Management - IT Project Management Consulting
 
Yeah, but then it is driven by the duration, which is necessary for billing. I want it to be - this will take 3 hours, but you have 3 days to do it.
 
Then you'd use absolute dates for the start and end, and would open the task to make the task NOT effort driven. Then you can post the 3h

D.E.R. Management - IT Project Management Consulting
 