ericbosman
IS-IT--Management
Hello,
I'm using MSProject 2007 Server for making a planning for a department. The department consists of multiple groups of programmers. I have found the way to make teams in MS Project, which is nice because i do not know which programmer is going to do which activity. But now i have the following problem. I want to see the resource usage of the team, but i see only the usages of the persons.
Example
Team A consist of Programmeur Piet and Klaas.
Piet and Klaas can work 8 hours a day
Activity 'programming X' costs 40 hours
Activity 'Programming Y' costs 40 hours
Both activities will be done in week 13 and both are assigned to Team A
In the resource usage i see
Piet - Availeble 40 hours, assigned 0 hours
Klaas - Availeble 40 hours, assigned 0 hours
Team A - Availeble 40 hours, assigned 80 hours (oversubscription of 100%)
What i want to see is
Piet - Availeble 40 hours, assigned 0 hours
Klaas - Availeble 40 hours, assigned 0 hours
Team A - Availeble 80 hours, assigned 80 hours (oversubscription of 0%)
Does anyone know how you can make this happen in MS Project?
Thanx in advance.
Eric Bosman
I'm using MSProject 2007 Server for making a planning for a department. The department consists of multiple groups of programmers. I have found the way to make teams in MS Project, which is nice because i do not know which programmer is going to do which activity. But now i have the following problem. I want to see the resource usage of the team, but i see only the usages of the persons.
Example
Team A consist of Programmeur Piet and Klaas.
Piet and Klaas can work 8 hours a day
Activity 'programming X' costs 40 hours
Activity 'Programming Y' costs 40 hours
Both activities will be done in week 13 and both are assigned to Team A
In the resource usage i see
Piet - Availeble 40 hours, assigned 0 hours
Klaas - Availeble 40 hours, assigned 0 hours
Team A - Availeble 40 hours, assigned 80 hours (oversubscription of 100%)
What i want to see is
Piet - Availeble 40 hours, assigned 0 hours
Klaas - Availeble 40 hours, assigned 0 hours
Team A - Availeble 80 hours, assigned 80 hours (oversubscription of 0%)
Does anyone know how you can make this happen in MS Project?
Thanx in advance.
Eric Bosman