Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations IamaSherpa on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Tasks seem to ignore project calendar

Status
Not open for further replies.

skm94

Programmer
Jul 13, 2009
1
US
I am in "teach myself Project" mode and have encountered a problem that has me perplexed.

I created a custom calendar for the project, cleverly called "Proj Calendar". This calendar defines Mon-Sat as work days. Mon-Fri work 10 hrs, 8-12, 1-5, 7-9. Sat works 8-12 and 1-5. Sunday is off. However, I defined a second "Work Week" called "Spec Sun". It consists of one Sunday (July 19) and defines it as 8-12, 1-5 work day.

When I look at the "Change Working Time" dialog box and click on any day, I get the correct hours.

I assigned this calendar to the project, and also to all four resources that I defined.

When I add a task, it seems to ignore this calendar. The task I added was given a Constraint of "Must Start On" and date of Sunday July 19 at 8:00 am. I left the Calendar set to None. The task duration is 4h.

I assigned one resource - me - to the task. I have the "Proj Calendar" assigned to my resource record.

When I add the task, the GANTT chart shows it starting 7/19 at 8:00 am (as I would expect) but not finishing until 7/20 at 12:00 pm. It acts like Sunday is a non-work day and the task is thus done on Monday morning.

When I change the task to explicitly give it the "Proj Calendar", then it shows the task ending 7/19 at 12:00 pm as I would expect.

OK - so I could simply assign the calendar to every task, but the Project Help (and MS' website) explicitly say that a task with a calendar of "None" uses the project calendar by default. I even display the "Task Calendar" column and it shows "None".

I don't want to have to manually change every new task to the correct calendar. Am I missing something? Everything I have read seems to say my task should have the correct project calendar.

Thanks
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top