I'm new to project en struggeling to get the amount of hours that are assigend to a task distributed to a resource.
After leveling, a task with two subtasks with each 8 hours of work to be done, is being scheduled to 8 hours per day over a period of several weeks, because there are other task for the same resource.
Is it possible to get project to do this right?