Task Dependencies

Status
Not open for further replies.

sudip00

MIS
Dec 23, 2002
49
US
Hi, I have about 8 tasks scheduled in my project. Whenever I change the date for the task 1 or task 2, the dates for the future tasks do not change as they should. They are linked by Finish-to-start dependency which should chnage the date for underlying tasks.

Thanks in advance.
 
I tried to mimic your problem, bearing in mind I'm a newbie to MSProject.

The only way I can force the same symptoms is to have 'Must start on' constraints on the predecessor and the next task. But if you do that, you do get a scheduling conflict warning, which presumably you would have noticed?

Jim Brown,
Johannesburg,
South Africa.