strugglers
Programmer
hi all you expert MS Project users that have helped me tons in the past! )
Need your help once again for the following problem:
I have generated a customer report in MS Project that shows all tasks contained in 'work package A' which have predecessors that are outside of work package A, i.e. they are linked from a seperate work package (e.g. Work Package B) which is owned by someone else. In order to get this, I tick the 'predecessors' checkbox under 'task' on the 'details' tab of the custom report.
Although this works fine, the only attributes shown on the final report for the predecessor information is 'ID, Predecessor name, Type and lag'. This is ok but I need it to show the start date of the predecessor task plus other info. I've looked in the tables option to see if the data is pulled from a 'predecessors table' of some sort but no luck and looked under all other possible options but still can't find a way to taylor this information.
I assume the data is hard coded into MS Project and therefore can't be modified.
Please let me know if there is anyway of modifying this predecessor data because it is slowly driving me insane.
Thanks in advance for your help and taking the time to read this.
Regards (as always)
Matt
Need your help once again for the following problem:
I have generated a customer report in MS Project that shows all tasks contained in 'work package A' which have predecessors that are outside of work package A, i.e. they are linked from a seperate work package (e.g. Work Package B) which is owned by someone else. In order to get this, I tick the 'predecessors' checkbox under 'task' on the 'details' tab of the custom report.
Although this works fine, the only attributes shown on the final report for the predecessor information is 'ID, Predecessor name, Type and lag'. This is ok but I need it to show the start date of the predecessor task plus other info. I've looked in the tables option to see if the data is pulled from a 'predecessors table' of some sort but no luck and looked under all other possible options but still can't find a way to taylor this information.
I assume the data is hard coded into MS Project and therefore can't be modified.
Please let me know if there is anyway of modifying this predecessor data because it is slowly driving me insane.
Thanks in advance for your help and taking the time to read this.
Regards (as always)
Matt