Hi All,
Thanks for taking the time....
I have a table that contains two coulombs.
1) Proccess_Step
2) Expected_Time
Proccess_Step is a single step in a life of a file :
Step1 Send file to Manager
Step2 Print
Step3 Mailing
Step4 Questionnaires Returned
Step5 Data entry
..etc...etc..
Step20 Confirmation sent to Manager.
Expected_Time is the amount of days that is allocated to each step :
Step1 0 day
Step2 0 day
Step3 1 day
Step4 5 day
Step5 2 day
....etc...etc...
Step20 1 day
What I would like to do is make a calculation that will take the date when Step1 has been started, and add to that each of the 'Expected_Time' for each of the steps.
This would then produce a forecast that can say, at what step we should be at on what day. So then we can easily see if we are behind, or ahead of schedule in the life cycle of the file.
All I would need is to find a way to make a query that would just add the days together in the correct order. So I would have a query that would produce the following.
Step1 0
Step2 0
Step3 1
Step4 6
Step5 8
....etc...etc...
Step20 120
Once I have the "Accumulative value" for each step then I can do the rest no problem...
Thanks alot for reading all this, and hope that is makes
sense.
Derick.
Thanks for taking the time....
I have a table that contains two coulombs.
1) Proccess_Step
2) Expected_Time
Proccess_Step is a single step in a life of a file :
Step1 Send file to Manager
Step2 Print
Step3 Mailing
Step4 Questionnaires Returned
Step5 Data entry
..etc...etc..
Step20 Confirmation sent to Manager.
Expected_Time is the amount of days that is allocated to each step :
Step1 0 day
Step2 0 day
Step3 1 day
Step4 5 day
Step5 2 day
....etc...etc...
Step20 1 day
What I would like to do is make a calculation that will take the date when Step1 has been started, and add to that each of the 'Expected_Time' for each of the steps.
This would then produce a forecast that can say, at what step we should be at on what day. So then we can easily see if we are behind, or ahead of schedule in the life cycle of the file.
All I would need is to find a way to make a query that would just add the days together in the correct order. So I would have a query that would produce the following.
Step1 0
Step2 0
Step3 1
Step4 6
Step5 8
....etc...etc...
Step20 120
Once I have the "Accumulative value" for each step then I can do the rest no problem...
Thanks alot for reading all this, and hope that is makes
sense.
Derick.