chicago25624
IS-IT--Management
- Apr 8, 2013
- 8
When I open my Master Project, with 200+ Projects imported into it, the view will not show expanded, on the first try. I have to Expand, Collapse, and Expand to get the proper view.
Al Bahar LVZTW 100% 135.82 days 135.82 days
Major Milestones 100% 93 days 93 days
PreStart 100% 100 days 100 days
Start On Line 100% 33.82 days 33.82 days
Then I have to expand it to get the actual view
Al Bahar LVZTW 100% 135.82 days 135.82 days Thu 7/12/12 Tue 1/15/13
Major Milestones 100% 93 days 93 days Fri 9/7/12 Fri 1/11/13
DTO Engineering Completion date established 100% 0 days 0 days Fri 9/7/12 Fri 9/7/12
SOL 100% 0 days 0 days Mon 12/3/12 Mon 12/3/12
RTS 100% 0 days 0 days Fri 1/11/13 Fri 1/11/13
PreStart 100% 100 d 100 D Thu 7/12/12 Thu 11/29/12
PO Placement 100% 1 hr 1 hr Thu 7/12/12 Thu 7/12/12
Conversion to Order 100% 10 days 10 days Thu 7/12/12 Thu 7/26/12 6
LQBJH Kick Off Meeting 100% 1 hr 1 hr Mon 7/23/12 Mon 7/23/12
Order Update 100% 12 wks 12 wks Fri 9/7/12 Thu 11/29/12
Generator 100% 16 wks 16 wks Mon 7/23/12 Mon 11/12/12
Al Bahar LVZTW 100% 135.82 days 135.82 days
Major Milestones 100% 93 days 93 days
PreStart 100% 100 days 100 days
Start On Line 100% 33.82 days 33.82 days
Then I have to expand it to get the actual view
Al Bahar LVZTW 100% 135.82 days 135.82 days Thu 7/12/12 Tue 1/15/13
Major Milestones 100% 93 days 93 days Fri 9/7/12 Fri 1/11/13
DTO Engineering Completion date established 100% 0 days 0 days Fri 9/7/12 Fri 9/7/12
SOL 100% 0 days 0 days Mon 12/3/12 Mon 12/3/12
RTS 100% 0 days 0 days Fri 1/11/13 Fri 1/11/13
PreStart 100% 100 d 100 D Thu 7/12/12 Thu 11/29/12
PO Placement 100% 1 hr 1 hr Thu 7/12/12 Thu 7/12/12
Conversion to Order 100% 10 days 10 days Thu 7/12/12 Thu 7/26/12 6
LQBJH Kick Off Meeting 100% 1 hr 1 hr Mon 7/23/12 Mon 7/23/12
Order Update 100% 12 wks 12 wks Fri 9/7/12 Thu 11/29/12
Generator 100% 16 wks 16 wks Mon 7/23/12 Mon 11/12/12