I have some very lengthy projects involving equipment and people
moves. With the people moves I have to perform staging and often
have to rework based on a circular relationship with up to 25 events in the predecessor chain.
MS Project will tell you that you have a circular
relationship, but you must manually find each task and write it down to
find all those that are part of the chain.
Is there a way to view the whole sequence of a particular chain?