CRXI
The report has a field proj_due_date.
We need to define status of the project
and number of days (overdue) that past proj_due_date
Status
If more than 20 days between current date and proj_due_date then status is ‘In Development’
If less than 20 days between current date and proj_due_date then status is ‘Anticipated’
If current date past proj_due_date then status is ‘Late’.
Give me please an idea how to make it?
Thank you!
The report has a field proj_due_date.
We need to define status of the project
and number of days (overdue) that past proj_due_date
Status
If more than 20 days between current date and proj_due_date then status is ‘In Development’
If less than 20 days between current date and proj_due_date then status is ‘Anticipated’
If current date past proj_due_date then status is ‘Late’.
Give me please an idea how to make it?
Thank you!