start times for tidal dependant projects

Status
Not open for further replies.

mawibri

Technical User
Jan 3, 2007
2
GB
Gents

Whilst not a super user of Microsoft project I have a little hard won experience as I have used the system mainly for scheduling since 1997.

My question is..How do I display columns with start and finish times (as in 14.35or 09.30) for tasks that start at a particular time in the day. (this is due to marine projects being tidal dependant)

Mark B
 
Ok Guys dont waste time i found it....you just change date formate to show day and time.
 