staffing by qualifications and resource count

Status
Not open for further replies.

itasueb

MIS
Mar 11, 2005
29
US
I have projects set up where subtasks correspond to individual workers/resources. Can I set up a subtask so that it can only be staffed by qualified rosources (for example, supervisors vs. technicians)? I also want to be able to get a count of the total number of supervisors and technicians that I have scheduled across all tasks for a given day. Is Project capable of doing these? If so, how would I accomplish this?
 
Sorry ... you are the only person who can identify the resource qualificatins (and, by extension, the resource) assigned to a task.

I suppose that, technically, it should be possible to code tasks with certain attributes and to code resources with attributes and then look for a best-match -- but that sounds a lot like computer dating to me and I think in the case of project management you're better off working with "arranged marriages".
 